Fort Morgan: City council looking at plan B for stalled Northern Integrated Supply Project

A picture named nisp2.jpg

From The Fort Morgan Times (John Brennan):

The city’s participation in the project would cost it more than $30 million over about 12 years after the project gains a permit, and city and water board officials have said it would ensure a reliable supply of water sufficient for future growth of the city. The project has been stalled, however, in the permitting process by the U.S. Army Corps of Engineers, due at least in part to objections from opponents of the project who claim NISP will damage the Poudre River. The city water advisory board has always strongly recommended that the city continue to be a part of NISP. No further information on the discussion regarding alternate options was provided in the council agenda packet for Tuesday’s meeting.

More Northern Integrated Supply Project coverage here and here.