From The Pueblo Chieftain (Chris Woodka):

A district formed to fix Fountain Creek is moving ahead with a road map to build flood control dams between Fountain and Pueblo. The entire process could take 3-12 years to complete, with the type of structures chosen and the availability of money the determining factors.

On Friday, Larry Small, executive director of the Fountain Creek Watershed Flood Control and Greenway District, broke down the process into bite-sized pieces for the board, which was formed five years ago by the state Legislature to resolve Fountain Creek differences between Pueblo and El Paso counties.

Phase 1 would be to compare three alternatives that were modeled in a U.S. Geo­logical Survey study completed this year. It would cost $60,000 and take up to a year to complete. Those include a large dam, a series of about 10 smaller dams or several midsize dams that would capture about the same amount of water.

“Maybe building fewer and bigger dams may be better than 10 small dams,” Small said.

Small said other alternatives in the USGS study either provided only local protection on other parts of Fountain Creek, or no protection at all to Pueblo in the event of a large flood. The study would corroborate past studies and identify — but not solve — issues with each of the alternatives. It would also use the USGS study to provide a visualization of floods of varying intensity, Small said.

The next phase would then compare the options by looking at engineering, easements, permits, costbenefit analysis and other factors.

“We want to be in a position that will allow us to begin building when the money becomes available,” Small said.

That money will start coming when Colorado Springs begins payment of the bulk of $50 million that it agreed to pay the district under Pueblo County’s 1041 permit for Southern Delivery System. The funding for the study would come from prepayment of nearly $300,000 in interest on the $50 million under the terms of the 1041 permit.

Pueblo County Commissioners and Colorado Springs still are negotiating the details of the prepayment, said Commission Chairman Terry Hart.

“What we’re trying to do is pave the way for the money, so the project can move forward,” Hart said.

More Fountain Creek watershed coverage here and here.