Construction of #Thornton Pipeline underway in #Windsor and #Johnstown — The #Loveland Reporter-Herald

Thornton Water Project route map via ThorntonWaterProject.com

From The Loveland Reporter-Herald (Pamela Johnson):

Contractors are building 7 miles of the Thornton Pipeline in Windsor and Johnstown, including boring a 250-foot-long section under the Poudre River.

“We’re doing sections in jurisdictions where we have agreements,” said Todd Barnes, spokesman for the city of Thornton.

“We wanted to get this in the ground before their developments, so we wouldn’t have to tear up new developments. We wanted to make it as efficient and effective as possible,” he said…

That elected board, in February 2019, denied the required permit for construction of the pipeline piece north of Fort Collins.

Thornton appealed that decision in 8th Judicial District Court. Last month, a judge upheld that denial based on three land use criteria. He did rule in Thornton’s favor on an additional four land use points, but the net ruling was to uphold the decision to deny the permit.

Officials with Thornton have not said if they plan to appeal that ruling, a request that would need to be filed by April 5, or change its permit request and reapply in Larimer County…

But they have said they are committed to transporting their water to Thornton.

For the sections of the pipeline running through unincorporated Weld County, Thornton has applied for a special review permit. That is scheduled before the Weld County commissioners May 5.

And in Windsor, Johnstown and Timnath, the city worked out construction and permanent easements that allow work to be underway, Barnes said.

In early 2020, construction began in both Johnstown and Windsor, 3.5-mile-long stretches of the pipeline in each of the towns, with Scott Contracting of Centennial as the general contractor.

The Johnstown piece is nearly complete, with one major section left that involves boring a tunnel for the 42-inch-diameter pipeline below the Little Thompson River, according to information from project manager Michael Welker and Justin Schaller, construction manager with Ditesco, a company hired by Thornton for onsite construction management.

Construction is active in Windsor, running parallel to County Road 13 on the east side of the road from just north of Colo. 392 to Crossroads Boulevard.

Crews on Wednesday were actively boring and building a horizontal shaft under the Poudre River for the pipeline.

Working from a site along the Poudre River Trail, workers had bored about 85 feet of the 250-foot section that will extend under the river. They are building a support structure and placing the pipeline inside. The pipe itself is metal with a concrete lining, with 50-foot-long sections welded together.

A week ago, crews finished boring the pipeline under Colo. 392…

The overall $428 million project is expected to be completed in 2025, Barnes said, with other sections completed as Thornton receives permits.

Once the pipe is laid, crews will reclaim the land, whether it is returning vegetation, working on wildlife mitigation or preparing fields for planting or grazing.

Leave a Reply