New Snowmass #wastewater plant almost done — The Aspen Daily News

Wastewater Treatment Process

From The Aspen Daily News (Steve Alldredge):

The district’s new, $27 million-plus wastewater treatment facility is nearing the end of its finishing touches after a three-year construction process. A ribbon-cutting ceremony for the new plant is tentatively set for Thursday.

Financed by a mill levy approved by the SWSD’s voters in May 2016, the facility was completed in March, whereupon the old plant was retrofitted to work in tandem with the new plant. Now, both facilities are online and working as designed, according to Hamby.

Some $23.3 million in bonds were sold for the project; the additional $4 million for the retrofitting of the old wastewater plant was financed through development-fee revenue from Snowmass construction projects, the district manager said.

In a tour of the new plant last week, Hamby beamed with pride as he described the reasons for the new plant, the complicated construction process of integrating the two plants and how SWSD employees accomplished retrofitting the old plant themselves…

While the plant took three years to build, the actual work started in 2013 when SGM, the Glenwood Springs-based company of consulting engineers, began talking to SWSD about new regulations that had recently been passed in 2012 in Colorado to reduce nutrient pollution in lakes, rivers and streams.

Regulation 85 by the Colorado Department of Public Health and Environment regulates nutrient discharges such as nitrogen and phosphorus and requires wastewater treatment plants to reduce both substances in the water that they discharge.

In the beginning, SGM and SWSD considered retrofitting the existing SWSD wastewater plant that was originally constructed in 1968 after the Snowmass ski area opened and then modified since then with additional construction.

A challenge for SWSD and the design and construction companies working on the new plant was the fact that the existing wastewater plant had to remain in operation while the new one was being constructed in order for Snowmass to meet current water regulations.

Because of this, the project was built in phases over the three-year period.

“Both plants have to be run in tandem to make this work, so we first had to build this new plant and put it online,” explained Hamby.

“Once it was constructed, we took the old plant offline, retrofitting it with new equipment, but we also had to remove a lot of the equipment that was over there. Our own people did the retrofitting work so it is really extraordinary to me that the people that maintain the plant also took responsibility to build basically a new plant inside,” he said.