From The Pueblo Chieftain (Chris Woodka):
It’s not clear whether the Southern Delivery System will be up and running by the end of April as Colorado Springs desires.
“We’ve seen significant movement, and the commissioners understand the sense of urgency,” said Pueblo County Attorney Greg Styduhar. “But that does not mean we will not continue to apply the same critical eye and comprehensive analysis we have used so far.”
Pueblo County, through its 1041 permit, might not have filled in all the boxes associated with turning on the water by that time, and has been working with Colorado Springs Utilities to complete the checklist. But it has taken time to work through issues, particularly the question of stormwater.
“Both sides have been working diligently and there have been some concessions, but no meeting of the minds,” Styduhar said. He said a final version of an agreement should emerge in the next few weeks, and the commissioners would like to give the public the opportunity to comment.Once a deal is reached, the public process could add another month for more review.
For almost a year, the county and Utilities have been negotiating an IGA that would allow SDS to start up. The meetings started as an alternative to a “show-cause” hearing on whether Colorado Springs Utilities was meeting all of its commitments under the 1041 agreement. Few details of the talks have emerged up until this week.
Meanwhile, the pipeline from Pueblo Dam to Colorado Springs already has been pressed into service, twice, to supply Pueblo West, which along with Security and Fountain is an SDS partner. Testing continues and Colorado Springs wants to fire up SDS by the end of April, when testing ends and warranties kick in.
Anxious to get things moving, Colorado Springs Mayor John Suthers this week revealed a proposal to Pueblo County that puts more than $450 million into play over 20 years to fix drainage problems on Fountain Creek. It also would pave the way to release $50 million over five years to build flood control structures on Fountain Creek between Colorado Springs and Pueblo.
The offer increases the amount of money on the table, the range of projects and the time frame, all of which Pueblo County has continued to fight for in negotiations. Styduhar agrees with Suthers that it would be an enforceable contract, citing Supreme Court decisions that back that viewpoint.
The question is timing.
“Certainly, there is a time crunch,” Styduhar said. “But it’s still important to look at it with
a critical eye.”