Greeley: Leprino cheese factory turns dirt for new wastewater plant

A picture named wastewatertreatmentprocess.jpg

From The Greeley Tribune (Chris Casey):

Leprino has also begun construction of the core and shell building for the wastewater treatment plant at 1133 Ash Ave., by Glacier Construction, for a total valuation of $1.56 million. Nick Opper, Leprino’s Greeley plant manager, said the three-phase construction is “on time, and we’ve got a lot of people working on the site right now.”

More wastewater coverage here and here.