Arkansas River basin: Water year 2011 has yielded the second largest import of water through the Boustead Tunnel since project water started moving in the 1970s

fillingjugswithwateratbousteaddedicationchieftain.jpg

From The Pueblo Chieftain (Chris Woodka):

The Fry-Ark Project has brought over 98,640 acre-feet of water this year, about 4,500 more acre-feet than was projected in May, when allocations were made…

Fort Lyon Canal, the largest ditch in the valley, will get an additional 1,700 acre-feet. The water comes on top of nearly 60,000 acre-feet already being delivered to farmers through the Fry-Ark Project. Late runoff and a heavy snowpack contributed to the second-largest import of Fry-Ark water since diversions through the Boustead Tunnel began in the 1970s…

Because Arkansas River flows stayed above 700 cubic feet per second through Aug. 15, no Fry-Ark water was needed to maintain the Upper Arkansas voluntary flow program, Vaughan added…

Basinwide, more than 200,000 acre-feet of water has been imported this year through transmountain tunnels and ditches, well above the average of about 136,000 acre-feet, said Pat Edelmann, of the U.S. Geological Survey. Twin Lakes has imported about 62,000 acre-feet and continues to move water. The Homestake Project has brought over 32,000 acre-feet.