From email from Reclamation (Kara Lamb):
Earlier this week, we increased the releases from Green Mountain from 200 cfs to 300 cfs. The change was made in four installments of 25 cfs increases: two on Monday and two on Tuesday. Because the Shoshone Power Plant maintenance work is diminished, the lower release from Green Mountain is not necessary. As a result, we will be releasing around 300 cfs through the Holidays.