The City of Montrose scores $400,000 grant from @CWCB_DNR for Uncompahgre River through town

River Bottom Park Uncompahgre River. Photo credit: PhilipScheetzPhoto via the City of Montrose

From The Montrose Daily Press (Andrew Kiser):

Parts of the Uncompahgre River have become “unstable” and “injured” over time due to past land use practices, leaving some areas packed with landfill material like debris and rubble, City Engineer Scott Murphy said.

But now, the City of Montrose will be able to refine portions of the river, in part due to a $400,000 grant given to the city by the Colorado Water Conservation Board (CWCB). The funds come through the Colorado Watershed Restoration Program to enhance the Uncompahgre.

The grant will begin the first phase of river restoration improvements for 0.65 miles of the Uncompahgre within city limits…

Additionally, aerial images have shown the river channel has migrated around 400 feet in some places over the past 50 years, Murphy indicated.

“It’s a pretty unstable breach of the river which is bad for the habibat because once the fish habibat gets established it gets wiped out as the river moves,” he said.

City of Montrose grant coordinator Kendall Cramer also said the Uncompahgre has experienced flow modifications and encroachment, which has developed a wider channel, bank stabilization issues and a lack of aquatic and riparian habitat.

“It’s an excellent project that’s going to enhance the river corridor,” Cramer said. “It’ll invest in the Uncompahgre River, which is one of our greatest assets in terms of tourism and recreation.”

He added the project will fix those problems as well as create better aquatic environments, stabilize the river banks and give the public better access to the water.

The city is hopeful this project will be the first step in receiving a gold medal fishery designation within the Uncompahgre River, Murphy said. Once completed, this section of the river will join a section of the Gunnison River which connects to the Black Canyon of the Gunnison National Park and joins the Gunnison Gorge…

The project design is being done by Ecological Resource Consultants, which won the bid for it in 2017. The River Restoration Committee and volunteers have helped the project come to fruition and have given input on the design, Cramer said.

The city anticipates construction to begin in winter of 2019-2020. Due to the river flow, work has to be completed within a four-month timeframe of November to February, when the water is at its lowest point.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.