Here’s the release from Denver Water:
Denver Water plans to improve the safety and reliability of its Ashland Reservoir site by building two new underground water storage tanks. The design for the site is being developed and construction is scheduled to begin in early 2013. Neighbors will notice more activity at the site as Denver Water staff members and contractors visit the site as part of the design process.
Western Summit has been hired by Denver Water as the construction manager for the project. As part of a phased project, Western Summit will demolish one of the two existing tanks and build a new tank in its place. Once that tank is in service, the second tank will be demolished and another tank built in its place. The two tanks cannot be demolished at the same time because the water stored at the site is needed for customers and for fire protection. The entire project is scheduled to run through 2017. The contractor for the project will be required to follow work hours, as set forth by the City of Wheat Ridge.
Large portions of the berms on the west and east sides of the site will be kept in place to reduce noise from demolition and construction. Part of the south berm will be removed initially for access to the site off of 29th Avenue. Additional sections of the south berm may be removed for use as a storage area for the project.
Soil removed from the Ashland site will be hauled to 20th and Quail Street for storage.
Once completed, the site will appear different from the existing site. The new tanks will be circular and smaller than they are now. The new tanks will have a smaller footprint, which will create a larger landscaped area on the south side of the property. The existing chain link fence will be removed and will be replaced by a black, 8-foot-high ornamental steel fence.
History of the site
The Ashland site date back to the 1890s. At that time, open air reservoirs with earthen bottoms were located at the site.
In the 1910s and early 1920s, concrete floors and wood roofs were added to the reservoirs.
In the mid 1960s and early 1970s, the wood roof was replaced with a precast concrete roofing system.
Despite routine maintenance and significant repairs, the existing tanks have experienced leaks, and some of the precast roof sections have cracked. The tanks at this site have reached beyond the end of their useful life and continued repair to the existing structure is impractical.
Additionally, as improvements have been made to Denver Water’s delivery system, it has been determined the existing 41 million gallons of storage at the site can be reduced to 20 million gallons.
When Ashland was constructed, it was one of a handful of storage sites for treated water. Denver Water now has many treated water storage tanks in its delivery system.
From The Denver Post (Emilie Rusch):
The Ashland Reservoir in Wheat Ridge is getting a $37 million upgrade over the next three years. Contractors for Denver Water began demolition earlier this month of the reservoir’s west underground storage tank. Once a new west tank is back in service, the east tank also will be torn out and replaced.
More infrastructure coverage here.
Like this:
Like Loading...