Buena Vista: Board of Trustees approves Nestlé’s offer to share the company’s Arkansas River pipeline crossing

A picture named nestlehaffeepipelinec.jpg

From The Chaffee County Times (Kathy Davis):

Town engineer Rachel Friedman will work with Nestlé during the construction. After the water pipeline is completed, Nestlé will convey the pipeline to the town. The agreement with Chaffee County grants an easement on its property on the Arkansas River. Also approved was an agreement with Paul and Rohnda Moltz for an easement on their property underneath the river. As of this meeting, the town had not heard from the U.S. Army Corps of Engineers regarding an application for a permit for the construction of a pipeline under the river.

According to Friedman, the town’s water master plan documents the need for additional water for future annexations anticipated within the town’s three-mile planning area, including Johnson Village.

More Nestlé Waters North America Chaffee County Project coverage here and here.