Brighton sanitary sewer rehabilitation project in the works, it should finish by year end

sewerusa.jpg

From The Brighton Blade:

The project is expected to start on the south side of Bridge Street, near Main Street, and work east. This portion should take about two weeks. The project then moves to the north side of that intersection and moves east. The work should be done by the end of the year. When it’s finished, the city says customers will have a new, rehabbed sewer system. Affected customers will get 24 hours notification of pending work from the contractor, Western Slope Utilities.