Telluride water system update: Raw water pipeline construction has started

pipeline.jpg

From The Telluride Watch (Gus Jarvis):

Telluride Town Attorney Kevin Geiger was happy to report last week that work on the raw water pipeline near the Bridal Veil Hydroelectric Power Plant has commenced, and once completed it will be the final piece of pipeline infrastructure needed to transport fresh water from Blue Lake, above Bridal Veil Falls, down to the two-acre site below the falls where the Pandora Water Treatment Facility will be located.

Crews will install a new horizontal water pipeline along with new trestles about 250 feet away from the Bridal Veil plant and then install vertical pipe that will transport the water to the bottom of a cliff. At that point, the line will be connected to a raw water pipeline that was installed last summer, just below Black Bear Pass Road, that runs to the water treatment facility site.

While the water pipeline infrastructure inches toward completion, Geiger said construction of the actual water treatment plant will start soon, as well.

“Most of the infrastructure is in from Blue Lake to the power house,” Geiger said. “A little segment, which will be difficult and challenging, needs to be completed and then actual construction of the water treatment plant needs to be completed. We think we will be breaking ground on that later this summer or fall.”

More infrastructure coverage here.