
From The Pueblo Chieftain (Chris Woodka):
Work is resuming on a dangerous portion of Fountain Creek through Pueblo.
The Army Corps of Engineers is overseeing a $750,000 project to install articulated concrete blocks — held together by cable in a mat and anchored to the ground — along the Fountain Creek bank near the 13th Street Exit on Interstate 25.
Work should be complete within three months and Pueblo contractor Pate Construction is doing the work while flows are low.
The project started in April, but was interrupted by heavy rains in May and June that increased flows on the Fountain to well above normal for more than six weeks. Waters only recently receded to the point where workers could get in the channel.
Fountain Creek will be temporarily rechanneled to the east of the area while work is underway, said Jeff Bailey, assistant city manager for stormwater.
The area had been secured by a gabion — wire-wrapped rock — which washed out during the September 2013 flood on Fountain Creek.
Fountain Creek hits the bank at a right angle at 13th Street, threatening railroad tracks and roadways in the area. While the Corps is responsible for the work and funds it, the city is the sponsoring agency and coordinates such things as local permits and access, Bailey explained.
There are several other projects still in the planning stages to repair damage from this spring’s flooding, Bailey said.
The city will be removing the debris such as large trees that were deposited at the Eighth Street bridge in the near future. “We need to get that clear so the water doesn’t start undermining the supports,” Bailey said.
The city is also working on restoring trails and repairing the berm at the flood detention pond behind the North Side Walmart.
Meanwhile, the Colorado Department of Transportation is working on projects to repair the Colorado 47 bridge and the trail in that immediate area, as well as clearing debris at the East Fourth Street bridge.