Trustees reject consultant recommendation about Meeker Water Supply Improvements Project

Yampa/White/Green/North Platte river basins via the Colorado Geological Survey

From The Rio Blanco Herald-Times (Niki Turner):

In an unprecedented move, the board voted against the bid award recommendations for the Meeker Water Supply Improvements Project from contracted civil engineer Olsson Associates. Olsson recommended awarding RNA Enterprises of Glenwood Springs for $340,948 and Ridge Electric of Grand Junction for $150,603 as the lowest bidders. Several trustees expressed concerns over the recommendation, as there was more than $100,000 difference between the low bid and the next highest bid, and the bid was not itemized.

Wyatt Popp of Olsson cautioned the board that the Department of Local Affairs (DOLA) grant funding received from the town would be at risk if the board chose to go with a higher bid. State statutes for DOLA funds require awarding the lowest bid as long as the bidders are responsive and qualified.

“Deviating from the process at this point in time is not recommended,” Popp said. Refusing to accept the recommendation risks losing approximately $300,000 in DOLA grant funds…

Town Attorney Melody Massih asked if there is a way to re-bid the project. Popp said that would require additional discussion with DOLA.