Southern Delivery System: The CWQCC will appeal judge’s ruling for project water quality permit

fountaincreekthrucoloradospringsfromdippity.jpg

From The Pueblo Chieftain (Chris Woodka):

The Colorado Water Quality Control Commission voted unanimously Monday to appeal the decision. The commission approved staff certification under section 401 of the federal Clean Water Act in 2010, after the decision was protested by Pueblo District Attorney Bill Thiebaut and the Rocky Mountain Environmental Labor Coalition…

“The 401 certification was fully discussed and we’re convinced we made the right decision, controls are in place and that Colorado Springs is in compliance,” said John Klomp, a former Pueblo County commissioner who sits on the state water quality board. Colorado Springs Utilities will join the state in the appeal, said spokeswoman Janet Rummel.

“We agree with the state of Colorado that the Pueblo district court decision was erroneous and believe the court of appeals will affirm the Colorado Water Quality Control Division’s issuance of the 401 water quality certification for SDS,” Rummel said…

Ross Vincent, of the local Sierra Club and the coalition, said the state decision is not appropriate. “The Water Quality Control Commission’s decision makes no sense to me,” Vincent said. “The state did a really sloppy job in its first review of the water quality impacts of SDS. The facts are pretty clear, and that’s why Judge Reyes ruled the way he did. It would be simpler, faster, and a whole lot less expensive for the state to go back to the drawing board and do the thorough water quality review that the law requires.