From The Durango Herald (Dale Rodebaugh):

A Colorado Water Conservation Board grant will cover $475,000, with the remainder coming from the Southwest Basin Roundtable’s share of the Water Supply Reserve Account. Ground breaking is scheduled Nov. 13. Water will be available for the district’s first customers next year, Steve Harris, the district’s engineer, said Friday. Long­range plans envision serving 400 square miles, first in southeast La Plata County and later southwest Archuleta County…

The pipeline will follow Bayfield Parkway from the roundabout on County Road 501 to County Road 509, then south along County Road 509 to County Road 510, where it will turn west…

The district’s water will come from the city of Bayfield treatment plant, the capacity of which is to be expanded from 1.5 million gallons a day to 2.5 mgd. The plant currently treats 900,000 gallons a day…

The first two miles of pipeline will be 14 inches in diameter to accommodate several laterals, Harris said.
“Once we get into the rural area, we’ll use 8­inch pipe,” Harris said.