From The Tri-Lakes Tribune (Ben Ferrell) via The Colorado Springs Gazette:

At its Nov. 16 meeting, the Board of Trustees approved a contract to perform the drilling and casing of a new water well for the town’s water system.

The new well, Well No. 10, will be based in the Arapahoe Basin and will be a depth of approximately 1,100 to 1,800 feet, depending on the determination of where the best draw of water would be. Public Works Director Tom Tharnish said the town’s present water consultant managed the bidding process since the contract required a specialized scope of drilling. The winning bid came in at $624,975 and was awarded to Layne Christensen Co.

Tharnish said the company, operating under a different name prior, had performed work on the town’s older wells in the past and was surprised three bids came back from the invitation.He said he expected one or two.

A follow-up contract to perform the tie-in of Well No. 10 to water treatment plant No. 4 and 5 will be presented to the board after the start of next year, since the new well will be located right outside the plant, Tharnish said.

Mayor Don Wilson asked if Well No. 10 would serve as a replacement for Well No. 9, which is presently offline due to the levels of radium detected and undergoing radium removal.

Tharnish said he hopes to have No. 10 operational and producing in March or April of next year and it would serve as the replacement to Well No. 9’s water production until No. 9 is back online that following fall.

This is the first of 15 major projects for the town’s water system which will be funded through the town’s recent Certificate of Participation issued.

The contract was approved 5-1 with Trustee Jamy Unruh having lost her connection to the virtual meeting and unable to vote.