Brush: New wastewater treatment plant online

brushwastewaterplan042012.jpg

From the Brush News Tribune (Katie Collins):

The project also is one of the most ambitious that the city has seen in years and as of exactly 10:20 a.m. on April 12, Brush’s newest state-of-the-art wastewater treatment plant is up and running, ready for all the dirtiest business that Brush can dish its way.

On hand to get the facility rolling were Brush Mayor Dan Scalise who, along with City Administrator Monty Torres and Wastewater Manger and City of Brush Director of Utilities Dale Colerick, opened the plant in official fashion that morning as Scalise ceremoniously turned the valve to allow wastewater to flow into the facility.
As of the opening ceremony, just 50 percent of the newest portion of the plant is seeing use as a few more processes are in need of completion, including the building of one more settling tank, completion of the UV filtering system, as well as additional fencing, seeding, grating and solids handling assembly…

On March 12, 2012, in fact, the Colorado Water Quality Control Commission opened hearings on proposed water quality standards for nutrient concentrations in the state’s rivers and lakes as well as limits on anyone who discharges into those waters. Limits were adopted and will be implemented over the next 10 years and the City of Brush’s newest plant was designed specifically to utilize new technologies in order to remove nutrients such as phosphorous and nitrates from the City’s discharge to the South Platte River.

More wastewater coverage here and here.