Lincoln Park/Cotter Mill superfund site update: Community Advisory Group has first meeting, 15-20 year decommissioning planned

cottermillcontaminationconcerndenverpost10232011

From The Pueblo Chieftain (Tracy Harmon):

A Community Advisory Group met for the first time Thursday, kicking off what will be a 15- to 20year process to decommission the Cotter Corp. Uranium Mill south of town.

The Cotter Uranium Mill opened in 1958, became a part of a Superfund cleanup site in 1984 and ceased processing uranium for yellowcake in 2006. Cotter officials plan to close the mill forever and have already torn down most of the buildings on site.

At the meeting Thursday, the 14-member advisory group was introduced to entirely new teams of U.S. Environmental Protection Agency and state health department officials who will help guide the clean up of the site.
“The community advisory group input is always useful to the EPA,” said Martin Hestmark of the EPA. “We are going to listen to you,” said Mario Robles, a project manager for the EPA.

Among members of the new group are Jackie Mewes, a Canon City resident who worked 26 years at the Rocky Flats Nuclear Weapons plant during production and closure. “There is a broken infrastructure here because I see that things are not followed up on for sometimes two to three years. The process and regulations need to be up to date and the EPA needs to provide facilitation,” Mewes said.

Joe McMahon will serve as group facilitator on behalf of the EPA. He told the group members, “You all have other hats but in these meetings you are representing the community.”

“Am I missing something or why don’t we have a member from Cotter?” asked group member Marvin Eller. “They can’t be all bad.” McMahon told Eller that the group probably will get input from Cotter officials but that likely will come through the state health department and not through an actual representative sitting on the board. The group will advise state and federal health officials on proposals but it will be up to those agencies to make final decisions on the cleanup process. Chris Urbina, health department executive director, told the group that a road map on how the cleanup will proceed should be ready within a month, giving the group time to organize. At that point, a year-long pause in work will come to an end and cleaning up the mill site will begin, he said.

From The Pueblo Chieftain (Tracy Harmon):

A new Community Advisory Group is ready to get to work and should give direction to cleanup efforts at the Cotter Uranium Mill.

After a nearly yearlong pause to form the group and establish a road map for the complicated decommissioning process, work can begin. The 15member group will meet with state and federal officials at 6 p.m. Thursday at City Hall, 128 Main St.

The group is made up of Colorado Citizens Against Toxic Waste members, City Councilwoman Pat Freda, Fremont County Commissioner Tim Payne, former Fremont County Commissioner Mike Stiehl and several other interested community members.

The group’s members will decide protocols for moving forward and will hear an update on the Cotter Mill site from state health department officials

From The Pueblo Chieftain (Tracy Harmon):

The Cotter Uranium Mill site is mostly a naked landscape these days. For the first time since it opened in 1958, no native Colorado ores are on the site.

“It is a historic milestone; the last pile of ore was moved last week,” said John Hamrick, mill manager. “We tore down the whole mill without any injuries and the only buildings left are the office, change house, maintenance shop and analytical lab.”

All the other mill buildings have been chopped, placed around the edges of the primary impoundment — at least 10 feet from a plastic liner to prevent punctures — and buried in dirt, Hamrick said. Even the boilers have been disposed of after they were filled with a cement slurry.

The mill continues to employ 29 workers, who are busy with environmental monitoring work and the massive report writing that must be done. They measure 100-plus water wells, surface water and air monitors. Hamrick said when the primary and secondary impoundment are capped for good, they will be completely dry repositories that are supposed to last 1,000 years. “We will have to make sure the cover material is impervious enough that if the plastic liner ever goes away, any release would be very slow,” Hamrick said…

believes the tailings and chopped-up buildings should stay where they are and not moved off site as part of decommissioning.

“There is no credible pathway where contamination can get out of the site into the community.

And out of 45 mills in the country, Cotter is one of the very few that has the plastic liner under the impoundment ponds,” Hamrick said.

“Before we have our license terminated there cannot be any remedial activities left and all the remedies that will be implemented have to be shown to be protective of human health and environment,” Hamrick said.

“Before we have our license terminated there cannot be any remedial activities left and all the remedies that will be implemented have to be shown to be protective of human health and environment,” Hamrick said.

From the Cañon City Daily Record (Rachel Alexander):

According to an analysis submitted to the Colorado Department of Public Health and Environment in November, removing tailings from the Cotter Corp., Uranium Mill site south of Cañon City would be prohibitive due to both cost and danger to workers, the public and the environment. Cotter submitted the analysis to CDPHE at the department’s request, said Cotter Vice President of Milling John Hamrick. It is part of the process of updating plans to decommission to the site. According to the analysis, there is an estimated 10,061,000 cubic yards of material in the company’s Main Impoundment, weighing about 15,292,720 tons…

Cotter used the example of the Moab, Utah, Uranium Mill Tailings Remediation Project to make its estimates. “That’s the only yardstick we have,” Hamrick said.

Using that standard, they estimate it would take 5.4 years to move the materials from the Cotter facility and would require 455 trucks or one 114-car freight train every day, five days a week to complete the project. The document estimates the cost of moving the tailings no more than 30 miles would be at least $895 million. The cost estimate was made understanding that no site has been considered or researched…

Gary Baughman, director of the Hazardous Materials and Waste Management Division of CDPHE, said leaving the impoundments in place and sealing the ponds for permanent storage are provisions contained within Cotter’s radioactive materials license.

More nuclear coverage here and here.