I am proud the U.S. Bureau of Reclamation heeded my calls and quickly approved the Arkansas Valley Conduit — Senator Mark Udall

Arkansas Valley Conduit Comanche North route via Reclamation
Arkansas Valley Conduit Comanche North route via Reclamation

Here’s the release from the US Bureau of Reclamation (Tyler Johnson):

Bureau of Reclamation Great Plains Regional Director Michael Ryan has signed the Record of Decision for the Arkansas Valley Conduit and Long Term Excess Capacity Master Contract Final Environmental Impact Statement. The selected alternative is construction of the Arkansas Valley Conduit using the Comanche North Alternative.

“This project will help water providers throughout the Arkansas River Basin meet existing and future demands,” said Ryan. “While funding details remain to be coordinated, it is prudent this project move forward to be in a position to take advantage of federal, state or local funding opportunities when they arise.”

The Arkansas Valley Conduit is a feature of the Fryingpan-Arkansas Project. It will provide treated water to communities in southeastern Colorado. When complete, the pipeline for the Arkansas Valley Conduit could be up to 227 miles long. The Comanche North Alternative includes three federal actions:

  • Construct and operate the Arkansas Valley Conduit and enter into a repayment contract with Southeastern Colorado Water Conservancy District.
  • Enter into a conveyance contract with various water providers for use of a pipeline interconnect between Pueblo Dam’s south and north outlet works.
  • Enter into an excess capacity master contract with Southeastern Colorado Water Conservancy District to store water in Pueblo Reservoir.
  • “For the many small rural water providers the conduit will serve, this critical step in the process of building the project is greatly welcomed. Facing the water quality and waste water discharge compliance challenges has been daunting for this area, and the congressional approval in 2009 and now the Record of Decision from the Bureau of Reclamation provide real hope for an effective and efficient way to meet those challenges,” said Bill Long, President of the Southeastern Colorado Water Conservancy District.

    A Record of Decision is a decision document; it concludes the environmental impact statement prepared in compliance with the National Environmental Policy Act. It does not provide or allocate funding for the project. Reclamation published the final environmental impact statement in August, 2013.

    “The District is grateful for this decision, which is one more milestone in a half-century journey to a clean water supply for southeastern Colorado. As federally-mandated standards have changed, the need for the solution the preferred alternative provides is even greater. The promise to build this piece of the project was first made in 1962 by President Kennedy and was restated in 2012, right here in Pueblo, Colorado, by President Obama. Now let’s move forward to the next phases of design and construction,” said Jim Broderick, General Manager for the Southeastern Colorado Water Conservancy District.

    For more information on the Record of Decision, please visit http://www.usbr.gov/avceis. To obtain a hard copy of the Record of Decision, contact Doug Epperly at (406) 247-7638 or depperly@usbr.gov.

    From The Pueblo Chieftain (Chris Woodka):

    The Bureau of Reclamation approved the final construction plan for the Arkansas Valley Conduit Thursday.

    “It’s been a long haul,” said Bill Long, president of the Southeastern Colorado Water Conservancy District, sponsors of the conduit. “This critical step in the process of building the project is greatly welcomed.”

    The record of decision for the project was signed by Michael Ryan, Reclamation’s regional director. The record of decision includes the environmental impact study for the conduit, but the next step will be to obtain funding from Congress to build the project.

    Long, a Bent County commissioner and Las Animas business owner, has been working to get the conduit built since he joined the Southeastern board in 2002. The conduit was included in the 1962 Fryingpan-Arkansas Project legislation, but never built because of the expense.

    “In the last few months, it’s become clear that this will help, not only with drinking water, but at the other end with wastewater quality as well,” Long said.

    Reclamation Thursday approved a record of decision for the Comanche North route of the 227-mile pipeline from Pueblo Dam to Lamar. The chosen route includes initial treatment at the Pueblo Board of Water Works’ Whitlock treatment plant and a pipeline that swings south of Pueblo near the Comanche power plant.

    The conduit will deliver fresh drinking water to 50,000 people in 40 communities east of Pueblo. It is estimated to cost $400 million, which would be repaid partly through revenue from Fry-Ark contracts.

    Also included in the decision is a master storage contract in Lake Pueblo for the Southeastern district and a cross-connection between north and south outlets at Pueblo Dam.

    The storage contract will set aside space for conduit participants and other water users in the district.

    The Southeastern district is focused on funding the project. Political wrangling delayed the record of decision and federal belt-tightening limited appropriations to about $2 million this year, rather than the $15 million the district hoped for.

    “I think this is a really important step forward, and I’m very happy,” said Jim Broderick, executive director of the Southeastern district. “We still have a lot of work to do in funding the project.”

    From the Colorado Springs Independent (Pam Zubeck):

    The Bureau of Reclamation signed the Record of Decision today for a project that’s been in the planning stages since Pueblo Dam was built in the 1960s.

    Part of the Frying Pan-Arkansas project, the conduit has never been built due to lack of money.

    U.S. Sens. Michael Bennet and Mark Udall, Democrats of Colorado, issued a news release after the ROD was signed, which follows approval of an Environmental Impact Study last year.

    Here’s a release from Senator Udall’s office:

    U.S. Senators Mark Udall and Michael Bennet welcomed today’s signing of the Record of Decision for the Arkansas Valley Conduit, which represents a major milestone for the project that will bring clean water to communities in southeastern Colorado. The decision comes after Bennet and Udall urged the Bureau of Reclamation to quickly approve the Conduit’s Environmental Impact Study (EIS) that was finalized last August.

    “I am proud the U.S. Bureau of Reclamation heeded my calls and quickly approved the Arkansas Valley Conduit. This project, the final component of the Fryingpan-Arkansas Project, will help strengthen Colorado’s agricultural economy, our quality of life and rural communities throughout southeastern Colorado,” Udall said. “Water is our most valuable resource in Colorado, and we need to make every drop count. This project will ensure we continue to smartly develop our water resources.”

    “Colorado knows well that water is an extremely precious resource, and the Arkansas Valley Conduit will help ensure families in southeastern Colorado have access to a safe and healthy water supply,” Bennet said. “Today’s announcement couldn’t be more important to southeast Colorado, and it demonstrates the Interior Department’s commitment to getting this project done. With today’s announcement, we are one step closer to completing this historic conduit that will benefit many future generations of Coloradans.”

    Udall and Bennet have led efforts to secure resources and move forward with the construction of the Conduit. In addition to advocating for quick approval of the EIS, the senators have written to the Department of Interior to provide adequate resources for construction of the Conduit in future federal budgets.

    The Arkansas Valley Conduit is the final component of the Fryingpan-Arkansas Project, a water diversion and storage project in the lower Arkansas Valley. Once constructed, the Conduit will deliver clean drinking water to families, producers and municipalities throughout Southeastern Colorado. Bennet and Udall worked together to enact legislation in 2009 authorizing the construction of the Conduit, and have pushed ever since for funding to keep the project on schedule.

    More Arkansas Valley Conduit coverage here and here.

    Leave a Reply

    Fill in your details below or click an icon to log in:

    WordPress.com Logo

    You are commenting using your WordPress.com account. Log Out /  Change )

    Google photo

    You are commenting using your Google account. Log Out /  Change )

    Twitter picture

    You are commenting using your Twitter account. Log Out /  Change )

    Facebook photo

    You are commenting using your Facebook account. Log Out /  Change )

    Connecting to %s

    This site uses Akismet to reduce spam. Learn how your comment data is processed.