NISP: “There’s communities that are growing that need that water” — Reagan Waskom

Map of the Northern Integrated Supply Project via Northern Water
Map of the Northern Integrated Supply Project via Northern Water

From 9News.com (Maya Rodriguez):

At the heart of the $500-million plan is the construction of two new reservoirs: Galeton Reservoir, northeast of Greeley, and Glade Reservoir, northwest of Fort Collins. Both are designed to provide water for the growing populations of several communities in Larimer, Weld, Morgan and Boulder Counties. Building Glade Reservoir would also involve the relocation of seven miles of Highway 287, at a cost of $45 million.

“We’ve got to figure out how we’re going to provide water for future generations and these communities – the 11 cities and towns and the four water districts – are taking a very proactive step in planning for their future,” [Brian Werner] said.

The water to fill both reservoirs would come from the Poudre River – diverting away about ten percent of that river’s annual flow and use it to provide water for an additional 80,000 to 100,000 households…

Reagan Waskom is with the Colorado Water Institute at CSU, which has taken no formal position on the project.

“We’re playing out in this one basin what’s going to happen all over the state,” Waskom said. “It’s an urban, environmentally conscious group of folks, that don’t want to see another depletion. There’s communities that are growing that need that water – that’s the tension: how much more can we take out of these rivers?”

The Army Corps of Engineers is taking public comment on the NISP until Sept. 3.