Water line construction starting up in Cortez — The Cortez Journal

Water infrastructure as sidewalk art
Water infrastructure as sidewalk art

From The Cortez Journal (Jacob Klopfenstein):

Water line construction and drainage improvement work will begin in Cortez after the Labor Day weekend, Public Works director Phil Johnson said Thursday.

About 3,900 feet of 6- and 8-inch waterline will be installed, as well as 245 feet of 12-inch storm drain line, valves, fire hydrants and other infrastructure items. Construction will start this week and is expected to continue until the end of October.

The affected areas are Henry Street from Main Street to Montezuma Avenue, Montezuma Avenue from Henry Street to Sligo Street and S. Market Street from Seventh Street to 10 Street. Storm drain work along Edith Street also will begin.

At their meeting Aug. 9, Cortez City Council members awarded a $496,774 contract for the project to D&L Construction of Cortez, which had the lowest of five bids, according to city documents.