Windsor town board OKs rate hike

Northern Integrated Supply Project (NISP) map July 27, 2016 via Northern Water.

From The Greeley Tribune (Sara Knuth):

The Windsor Town Board voted unanimously Monday to approve the second water rate increase of the year for residents as officials look to strengthen their plans to add more water supplies.

The increase will bring rates up by an additional 6.21 percent, a hike that will appear on water bills April 1. In December, the board approved an annual increase of 3.29 percent that will be reflected on the March bill.

For water users, the increase means average single-family monthly consumption charges will be about $38.37. In 2018, bills were $35.06 per month on average.

During Monday’s meeting, town board said they didn’t come to the decision to raise the rates easily.

When one resident expressed concerned about how the rate increase might impact residents, Mayor Kristie Melendez said town officials came to the decision over several meetings…

The town, which currently owns shares in the North Poudre Irrigation Company and the Colorado-Big Thompson Project, is seeking to strengthen its participation in the Northern Integrated Supply Project, a massive project that will result in two new reservoirs and serve 11 communities and four water districts along the Front Range…

As it stands now, Windsor owns 4,100 acre-feet of water. But it’s going to need another 15,800 acre-feet in the future to keep up with demand, officials said…

In the town’s agreement with Northern Water, which manages the supply project, the town is scheduled to pay $100 million to the project by 2026, Town Manager Shane Hale said. The town won’t have enough money on its own to pay for that, he said, so officials will need a base of between $30 million and $33 million to issue debt to help pay for the cost in the future.

Of the total cost Windsor will pay toward NISP, 12 percent will come from water users who will pay the rate approved Monday. The other 88 percent comes from town development fees.

But Hale said town officials didn’t want to place the burden solely on developers and discourage them from coming to Windsor.

Windsor has worked with consulting firms since 2009 to work on ways to secure water. Most recently, officials worked with Stantec Consulting to develop a plan to pay for Windsor’s place in the water supply project and operations, including collecting, cleaning, filtering, disinfecting and testing water.

From The Fort Collins Coloradoan (Jacy Marmaduke):

Windsor’s residential water rates will increase by 6.21 percent to help fund the town’s involvement in the Northern Integrated Supply Project…

The rate increase, paired with another increase that took effect Jan. 1, will raise the average single-family residential water bill from $35.06 a month in 2018 to $38.37 a month in 2019.

Windsor is one of 15 municipalities and water districts that will receive water from the Northern Integrated Supply Project, or NISP, a proposal to build two new reservoirs and fill them with Poudre River water. Participants are funding the costs of the project, and Windsor’s involvement will cost over $100 million, according to Mayor Kristie Melendez…

The town is looking to ratepayers to fund about 12 percent of the project cost. The other 88 percent will come from a water resource fee leveled on each new home in Windsor, an approach that Melendez called “growth pays for growth.”

[…]

NISP will supply about 3,300 more acre-feet if it jumps through all regulatory hoops. An acre-foot of water is equivalent to the average annual water use of 2 to 3 urban households.

In all, NISP is expected to provide about 40,000 acre-feet of water to its participants. Windsor’s share of NISP is the third-largest among municipalities involved in the project.

The two proposed NISP reservoirs include Glade Reservoir, which would be located near Ted’s Place north of Fort Collins, and Galeton Reservoir, which would be located northeast of Greeley.

For comparison’s sake, Glade Reservoir’s capacity of 170,000 acre-feet is about 108 percent of the capacity of Horsetooth Reservoir. Galeton would hold about 46,000 acre-feet.

The Army Corps of Engineers is expected to issue a record of decision on NISP in 2019. Affirmation from the Army Corps will likely trigger a legal challenge from NISP opponent Save the Poudre. Northern Water expects to begin storage in Glade Reservoir in 2025.

4 thoughts on “Windsor town board OKs rate hike

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.