Final pipeline pieces get put into place for Southern Water Supply Project II

The contractors for the Southern Water Supply Project II reached a significant milestone last month with the installation of the final portion of pipeline.

The final piece was placed along the 20-mile route near Carter Lake in southern Larimer County. The pipeline, funded by the City of Boulder, Left Hand Water District, Longs Peak Water District and the Town of Berthoud, will bring water supplies to those communities year-round.

While the installation of pipeline is complete, additional work remains. Northern Water technicians are installing and programming equipment for integration into its SCADA system, and testing of the pipeline segments for quality assurance is ongoing. Northern Water anticipates the pipeline will start carrying water to its destination at Boulder Reservoir in April.

Beyond the pipeline, however, work will continue on another important aspect of construction: reclamation of disturbed ground. The pipeline runs through easements on a variety of public and private properties, and reclamation crews will be working with those entities to ensure lands are reclaimed to their owners’ satisfaction.

Garney Construction was the lead contractor for the $44 million project.