Southern Delivery System: Construction starting up on the Juniper pump station

The new north outlet works at Pueblo Dam -- Photo/MWH Global
The new north outlet works at Pueblo Dam — Photo/MWH Global

From The Pueblo Chieftain (Chris Woodka):

There’s room in a $900 million water pipeline project for all sorts of businesses. Even brick-makers.

Joe Welte, whose grandfather founded Summit Brick and Tile in Pueblo in 1902, gave a brief account of his family’s business at Tuesday’s celebration for local contractors who have worked on the Southern Delivery System. The event also marked the beginning of work on the Juniper Pump Station, the final piece of SDS construction in Pueblo County. He concluded with a story about his brother Tom’s visit to an elementary school, where he asked students to build a wall using either klinkers — bricks deformed by heat — or straight bricks. The students chose straight bricks, saying the wall would tumble with klinkers on the foundation.

“Whether you are starting an education, planning your life or building for our water future, make sure that you use straight brick at the bottom,” Welte said.

Summit Brick is one of about 100 local companies that are benefiting from contracts for SDS, a water delivery pipeline from Pueblo Dam to Colorado Springs that also benefits Pueblo West. Its part is relatively small: 50,000 4-by-4-by-12-inch bricks for the facade of the Juniper Pump Station, which amounts to about two days’ production.

“With the downturn in the economy, this came at a good time,” Welte said.

The bricks played a symbolic role at Tuesday’s event, as representatives of local companies build a wall and received commemorative bricks — made in Pueblo County, of course.

The largest amount of local contracts went to ASI Constructors, which holds three contracts for $50 million. The company builds dams and other water projects all over the world.

“It’s not often that we get to participate in a project of this magnitude in our own backyard,” ASI President John Bowen said.

He touted the safety of the project, 68,000 man-hours without a lost-time accident, and economic benefit, $800,000 in wages, for his company alone.

Government officials from both El Paso and Pueblo counties, including newly elected state Sens. George Rivera of Pueblo and Bernie Herpin of Colorado Springs, attended the event as well.

From the Colorado Springs Independent (Pam Zubeck):

On Tuesday, the city kicked off construction of the Juniper pump station not far from the outlet from the dam that was built earlier as part of SDS. It’s one of three pump stations that, according to Colorado Springs Utilities, represent some of the largest components of the project; cumulatively, they’ll cost $76.5 million. A third of that will go to Colorado contractors. The prime contractor is Archer Western Constructors of Arlington, Texas.

To update, here are some notes on SDS’ progress, provided by Springs Utilities:

• The SDS pump stations will move water 1,500 feet in elevation from Pueblo Dam to the new water treatment plant under construction in El Paso County. At full capacity, SDS will be able to transport up to 96 million gallons of water per day (MGD) – 18 MGD to Pueblo West and the remaining 78 MGD to the El Paso County partner communities of Colorado Springs, Security and Fountain.

• Garney Construction of Kansas City, Mo., is installing a 0.3-mile, 90-inch-diameter pipeline that will link Pueblo Dam to the Pueblo West Metropolitan District and other project partners. After Colorado Springs, Pueblo West is the second leading beneficiary of the SDS project.

• Major SDS construction work commenced in Pueblo County in 2011 with the start of the new connection to Pueblo Dam. Since then 18 miles of pipe have been installed in Pueblo County and a total of 42 total miles installed project-wide. Recently, the SDS pipeline construction project through Pueblo West was recognized by Engineering News Record as the Best Water Project in 2013 for the mountain states region.

• Construction of the nearly $1 billion project is resulting in significant benefits to the local economy. To date, more than 300 companies and organizations in Colorado have helped plan and construct SDS, including 100 in Pueblo County. Of the more than $362 million spent to plan and build SDS, more than $289 million has gone to Colorado companies.

From The Colorado Springs Gazette:

When complete, the Juniper water pump station in Pueblo will have many motors and one of them will have the horsepower of four Formula 1 racing cars.

It will need it to pump water 1,500 feet in elevation from Pueblo Reservoir to Pueblo West, Fountain, Security and Colorado Springs. Juniper station at Lake Pueblo State Park will be one of three water pump stations needed to move up to 96 million gallons of water up hill 53 miles in the Colorado Springs Utilities’ Southern Delivery System pipeline…

The entire $1 billion project is expected to be completed by April 2016 and could pump 5 million gallons daily at first but with eventual capacity to pump up to 96 million gallons daily.

From the Colorado Springs Business Journal (Rebecca Tonn):

The Southern Delivery System starts construction of the Juniper Pump Station at Lake Pueblo State Park and the last remaining section of pipeline in Pueblo County on [October 29, 2013]. Area businesses that will perform work or provide materials to build SDS components in the county will participate in a brick-laying ceremony, from 2 – 3 p.m.

More Southern Delivery System coverage here and here.