#NISP update

Cache la Poudre River from South Trail via Wikimedia Foundation.

From The Fort Collins Coloradoan (Kevin Duggan):

The Larimer County Planning Commission on Wednesday heard details of plans for constructing and operating the project, which would include building Glade northwest of Fort Collins and laying 35.6 miles of pipeline to carry NISP water out of the county.

The information packet given to commissioners, including staff reports, environmental impact statements and comments from numerous government agencies, is 3,242 pages.

The packet includes more than 500 comments from members of the public, including groups and individuals who have been fighting NISP since it was proposed in 2004.

Concerns about the project and its impact to the Poudre River during federal and state permitting processes were raised again along with new issues on the county level by environmental group Save the Poudre and others.

Larimer County plans several hearings

Wednesday’s meeting was the first of three planned by the planning commission on NISP. It consisted of presentations by county staff members and representatives of Northern Water, the main proponent of NISP.

No public comment was taken. That will happen during hearings scheduled July 8 and 15. An additional meeting would be scheduled if needed to allow Northern Water time for rebuttal following the public comment, county officials said.

Northern Water is seeking a 1041 permit — named for the state law giving authority to local governments to make decisions on certain types of infrastructure projects — for NISP. The planning commission will make a recommendation on the application to the Board of County Commissioners, which will decide whether to grant a permit.

Three of the nine planning commission members recused themselves from the proceedings citing the potential appearance of impartiality or conflicts of interest: Anne Best Johnson, community development director for the city of Evans, which is a participant in NISP; Bob Choate, an attorney who might be called upon to give legal advice on the project to the Weld County commissioners; and Sean Dougherty, a Realtor who represents a landowner who might be affected by the project…

Under the county’s 1041 regulations, the county’s purview of NISP is limited to the siting of Glade and associated recreational facilities and the locations of four large pipelines that would carry NISP water through Larimer County.

The project must meet 12 criteria for approval, including that the project would not negatively impact public health and safety and the “proposal demonstrates a reasonable balance between the costs to the applicant to mitigate significant adverse (effects) and the benefits achieved by such mitigation,” according to the land-use code.

County development review staff members said the proposal meets the criteria and recommended approval of the permit with 82 conditions, including requirements for several reports and plans for addressing issues such as noise and dust during construction.

Northern Integrated Supply Project (NISP) map July 27, 2016 via Northern Water.

As part of the project, Northern would build recreational facilities that would be managed by the Larimer County Department of Natural Resources. The department manages recreation at Carter Lake and Horsetooth, Pinewood and Flatiron reservoirs.

Facilities at Glade would include a visitor center, campgrounds, hiking, fishing and boating. A four-lane boat ramp would be built on the southeast side of the reservoir.

The facilities would increase recreational opportunities as envisioned in county master plans, said Daylan Figgs, Natural Resources director.

Demand for access to recreation will likely increase as the county grows in the years to come, Figgs said. The facilities proposed by Northern would cost about $21.8 million. NISP would cover 75% of the cost, with the rest coming from the county directly or through partnerships.

[Nancy] Wallace said she was “struck” that the county might have to contribute to the cost of recreational facilities. NISP doesn’t appear to “give much to the county” other than its recreation components and water for Windsor and the Fort Collins-Loveland Water District, she said…

Christine Coleman, a water resources engineer with Northern, told the commissioners $49 million in NISP environmental mitigation work would be done in the county.

The final environmental impact statement for NISP estimated development of the reservoir could bring in $13 million to $30 million a year in economic benefits, Coleman said. The project would contribute $16.35 million to recreation facilities at Glade…

To keep water flowing in the Poudre, which can dry up in spots under certain circumstances, NISP would release water from Glade back to the river through a 1.3-mile pipeline.

The added water would flow 13 miles through Fort Collins before it is picked up by another pipeline upstream from the city’s wastewater treatment plant on Mulberry Street. The guaranteed flow through the city would be between 18 and 25 cubic feet per second.

“This will increase flows at the Lincoln (Street) gauge in Fort Collins and the Poudre River in eight out of 12 months in average years and 10 out of 12 months in dry years,” said Stephanie Cecil, a water resources engineer with Northern.

Water would be pumped into a pipeline running east to a pipeline along County Road 1 running south. The pipeline would affect some city-owned natural areas.

A fourth pipeline would carry water from Glade along a route known as the “northern tier” and connect with the county line pipeline.

The pipe would run through the Eagle Lake subdivision, sparking resistance to the proposal from local residents…

Cecil said the pipelines would require 100-foot easements, of which 60 feet would be permanent and 40 feet would be temporary for constructions. Property owners would be paid fair market value for easements, and surface disruptions would be reclaimed to pre-existing conditions or better.

NISP’s pipelines would range from 32 to 54 inches in diameter. The northern tier pipeline would carry about two-thirds of the water going to NISP participants, Cecil said…

What’s next for NISP in Larimer County

The Larimer County Planning Commission is scheduled to take public comment on NISP during hearings schedule July 8 and July 15 at the County Courthouse Offices Building, 200 W. Oak St. in Fort Collins.

Both meetings will begin at 6 p.m. Attendance will be limited to 50 people because of COVID-19 restrictions on gatherings.

Comments will be limited to 2 minutes per person. Borrowing, lending or grouping time will not be allowed. Groups and individuals who wish to speak in person or remotely must register at larimer.org/planning/NISP-1041.

The planning commission will make a recommendation on a permit for NISP to the Board of County Commissioners, which will decide on the application.

Hearings by the commissioners are scheduled:

  • 6 p.m., Aug. 17 – Presentations only; no public testimony.
  • 2 p.m. Aug. 24 (break from 5:30-6:30 p.m.)
  • 3 p.m. Aug. 31 (break from 5:30-6:30 p.m.)
  • 6:30 p.m. Sept. 2 – questions, final deliberation and decision
  • Information: http://larimer.org/planning/NISP-1041

    Northern Integrated Supply Project July 27, 2016 via Northern Water.

    From The Loveland Reporter-Herald (Pamela Johnson):

    Larimer County staff has recommended approval of a 1041 permit for the Northern Integrated Supply Project with requirements that include noise, water and air quality monitoring and mitigation during construction of its reservoirs and associated pipelines.

    Engineering, health department and planning staff members outlined that recommendation to the Larimer County Planning Commission on Wednesday during the first of a three-part public hearing for the reservoir project, which over the past decade has drawn vocal opposition and support.

    Northern Water hopes to build the water project on behalf of 15 water providers as a way to pull water in wet years, from both the Poudre and South Platte rivers, to store for when needed. All of the participants have water conservation plans and have reduced their water use by 10%, but still need future water supplies, according to Northern Water…

    The U.S. Army Corps of Engineers is responsible for the main permit to build the project — a decision expected sometime this year after more than a decade of evaluation. However, Larimer County does have some authority through its 1041 permit on certain aspects of construction of the reservoir and its associated pipelines as well as recreation on and surrounding the reservoir.

    The planning commission will make a recommendation to the Larimer County commissioners, who will hold a public hearing that is scheduled across three Mondays starting Aug. 17 and will end with a decision on whether to grant the 1041 permit.

    The first of the planning commission dates, Wednesday, was a presentation by Northern Water and by Larimer County staff. Public comment is slated for the next two hearings, scheduled July 8 and July 15…

    Some highlights of the presentation, from both county staff and Northern Water representatives, include:

  • The realignment of U.S. 287 north of Fort Collins is not part of the 1041 permit, but Larimer County is asking that the design take into effect the impacts on nearby county roads including the already dangerous intersection with U.S. 287 and Colo. 14.
  • Glade Reservoir would be able to store 170,000 acre feet of water with 1,600 surface acres and water that could hit 250 feet at its deepest. The reservoir would be 5 miles long, and the project would include four separate pipeline segments spanning a total of 35.6 miles.
  • Recreation at the reservoir would be detailed closer to construction to reflect trends and interests at the time but would include a mixture of boating, camping, fishing and trails that would help meet demands for a growing Larimer County population. Overall, Northern Water has proposed $21.8 million in recreation amenities and improvements, including a visitors center. Northern Water has committed to covering 75% of those costs through the project; the remainder would be covered through partnerships.
  • Northern Water would need to mitigate impacts on traffic that would range between 400 and 1,600 average daily trips during construction of the reservoir, up to 300 daily trips associated with construction of the pipelines and an average of 1,150 daily trips associated with recreation.
  • Larimer County would require traffic management, dust and noise mitigation plans, as well as groundwater monitoring. Construction would be limited to daytime, and the county would require private well monitoring to ensure that those water sources are not polluted.
  • County staff members believe any impacts on wildlife, wetlands, streamflow, fisheries and other natural resources would be mitigated by existing measures in a Fish and Wildlife Mitigation and Enhancement Plan that was approved by state officials in 2017, as well as through a water quality permit based on multiple studies and evaluations. The mitigation plan calls call for $53 million in improvements, including fish-friendly bypasses at diversion structures, a low flow plan to keep more water in the Poudre River through Fort Collins and enhancements to wetlands and wildlife habitat.
  • The project proposes swapping irrigation water from the Poudre River with water from the South Platte River, which will prevent “buy and dry” of farmland. This could keep more than 60,000 acres of irrigated farmland in production, according to Northern Water.
  • Northern Integrated Supply Project preferred alternative