Larimer County commissioners approve 1041 permit for #NISP by 2-1 vote — The Loveland Reporter-Herald

Cache la Poudre River watershed via the NRCS

From The Loveland Reporter-Herald (Max Levy):

Larimer County’s Board of County Commissioners voted 2-1 to approve a 1041 permit for the Northern Integrated Supply Project on Wednesday, with John Kefalas casting the lone “no” vote.

Explaining his dissent, the District 1 commissioner said he felt the 12 land use criteria used by the board fell short and failed to create a “level playing field,” although he acknowledged the board’s efforts to allow public comment virtually…

He discussed the projected impacts of climate change on the upper Colorado River Basin, and echoed the concerns of many commenters regarding the reduction in flow that the Poudre River could see from the creation of the Glade Reservoir.

He pointed out that Fort Collins, which is bisected by the river, has concerns about the flows in the Cache la Poudre.

“I acknowledge that Northern (Water) has done their utmost to look at mitigation and other impacts on the Poudre River ecology, riparian areas and natural areas,” he said. “There still remains the fact that the city of Fort Collins has concerns about the potential impact on the Poudre River.”

Commissioners Tom Donnelly and Steve Johnson each walked through the land use criteria and how the project satisfied them…

The vote on the permit came after an extensive public hearing — one session saw representatives of the Northern Water Conservancy District advocate for the project, two sessions invited public comment, and Northern Water representatives answered questions during a fourth session.

While a large part of the presentation Wednesday was taken up by the commissioners explaining each of their votes, the commissioners also heard from Northern Water representatives who asked for adjustments to some of the conditions placed on the proposal.

The commissioners agreed to include a suggestion by Northern Water that, if the alignment of a related pipeline had to be adjusted by more than 100 feet without a landowner’s consent, that section of the pipeline would again have to be reviewed.

They also agreed to include restrictions proposed by Northern Water on construction activities in the Eagle Lake area.

Here’s a photo gallery from the hearing via The Fort Collins Coloradoan.