Wellington: Boxelder basin floodplain update

A picture named floodplain.jpg

From the North Forty News (Cherry Sokoloski):

Phase I of the project, which will enlarge Clark Reservoir and widen the Inlet Canal flowing into the reservoir, should be mostly complete by the end of 2011, according to Larimer County engineer Martina Wilkinson. The $4 million project will be bid out in two separate contracts, she said…

When Phase I is complete, more than 200 homes in Wellington plus Eyestone Elementary and Wellington Middle School will no longer be in the Boxelder floodplain. The requirement for flood insurance in that area will “go away” once floodplain maps are revised, Wilkinson said, likely sometime in 2012.

On Dec. 16 at 10 a.m., the county commissioners will hold a work session to discuss Boxelder fees and boundaries.

More stormwater coverage here and here.