The Pagosa Springs Sanitation and General Improvement District board is moving ahead with wastewater pipeline

Wastewater Treatment Process
Wastewater Treatment Process

From the Pagosa Sun (Ed Fincher):

The Pagosa Springs Sanitation and General Improvement District board voted last week [week of November 25] to accept a bid from Hammerlund Construction Company for work on a pipeline and pumping stations needed to deliver wastewater from the town’s current lagoon site to the Pagosa Area Water and Sanitation District’s Vista treatment plant.

Art Dilione, special projects manager for Bartlett & West, the company tasked with handling the bidding process for the town, sent a letter to both town manager David Mitchem and Gregg Mayo, special projects director for PAWSD.

The letter, dated Nov. 19, explained how the project was originally bid on Oct. 2, but all of those bids came in well above the engineer’s estimate as well as the project’s budget, so those original bids were rejected and the project was rebid on Nov. 12.

More wastewater coverage here.