From KOAA.com (Jessi Mitchell):

A Colorado Springs delegation, headed by Mayor John Suthers, took a trip to Pueblo Monday, and stormwater was the topic of discussion with both Pueblo County commissioners and city councilors.

Commissioners talked with the Springs leaders at length about a new inter-governmental agreement that will make sure stormwater management is a priority for years to come. They are working quickly to finalize the details before turning on the Southern Delivery System…

So Colorado Springs and Pueblo County are talking it out. On Monday, Suthers showed off all his city’s progress towards stormwater management since he was elected last year, with a new $19 million a year mitigation plan. He says unlike broken promises in the past, an additional inter-governmental agreement will ensure those measures continue beyond his tenure, with assurances to spend more than $200 million on stormwater in the first decade.

Suthers says, “Rather than having the voters say, ‘no we don’t want to pay this,’ we will be contractually, and by court order, obligated to have a sustainable, appropriately funded stormwater system.”

Pueblo County commissioners still want more input in which stormwater mitigation projects come first, namely the ones that directly impact their constituents, but the governments say they are working together better now than ever before. “Hopefully reasonable people can find reasonable solutions without having to go to court,” says McFadyen, “and likely that will be an inter-governmental agreement with enforceability clauses that both parties can agree on.”

“These are tough problems,” admits Suthers, “but they need to be resolved and I think both sides definitely want to resolve them.”

The Colorado Springs group also presented to Pueblo city councilors Monday evening, talking specifically about Fountain Creek and the funds they have given to help dredge the sediment built up over the past year.

From the Colorado Springs Independent (Pam Zebeck):

Mayor John Suthers got an earful from Pueblo County commissioners Monday after laying out the city’s plan to deal with its stormwater problem.

The city is in a tiz, because Pueblo County now has leverage to force the city of Colorado Springs to make good on past promises to control storm runoff, which empties into Fountain Creek and brings sediment rushing down to Pueblo. The creek, overwhelmed by flood waters, already has claimed hundreds of acres of farmland.

Now, as Colorado Springs gets ready to activate the Southern Delivery System pipeline from Pueblo Reservoir, it must meet requirements of a construction permit, commonly called a 1041 permit, granted by Pueblo County in 2009.

On top of that, the city is facing a federal consent degree or court order to comply with federal Clean Water Act requirements for its stormwater system due to years of noncompliance.

“We’re going to solve this problem and not kick the can down the road,” Suthers told commissioners Monday afternoon at a meeting in Pueblo. “A federal consent decree or judgment cannot be ignored, and neither can an IGA [intergovernmental agreement] with Pueblo.”

Pueblo County Commissioner Terry Hart noted the Springs has “breached” promises to deal with stormwater in the past, most notably by doing away with the Stormwater Enterprise in late 2009. Suthers noted that came after a ballot measure was approved by voters, which essentially required the city deep-six the enterprise. He said the city’s new scheme, to carve out $16 million a year from the general fund with another $3 million a year contributed by Colorado Springs Utilities for 10 years, doesn’t rely on voter approval.

But Hart wants the IGA to extend well beyond 10 years. In fact, he proposed the IGA last for the life of the SDS project, which could be 30 to 40 years.

He also asked if Colorado Springs was willing to suspend activation of the SDS pipeline until the IGA is worked out. Not likely, Suthers said, due to warranties on the components of SDS.

Hart also suggested the city pump more money into Fountain Creek restoration beyond $50 million agreed to as part of the 1041 permit.

Suthers said he’s “nervous” committing the city “into perpetuity” but said an IGA could be hammered out that allowed for additional terms beyond 10 years if certain triggers are met.

Pueblo County Commissioner Sal Pace asked if Colorado Springs could commit a substantially greater amount per year than the $19 million now identified under the IGA, to which Suthers said the amount could go up to $25 million per year based on inflation. But he noted that huge increases, such as up to $50 million a year, aren’t likely.

On one thing everyone seemed to agree: The solution doesn’t lie in another court battle. Hart noted Colorado Springs could outspend Pueblo in court, and Suthers later told media that a lawsuit isn’t the answer. That said, Hart said he wants an “enforcement mechanism,” should Colorado Springs yet again fail to meet its promises, such as the authority of Pueblo to stop flows through SDS for noncompliance. That idea seemed to be a non-starter, although Suthers was willing to discuss another demand by Hart — to allow Pueblo County officials to participate in negotiations with the Environmental Protection Agency and the Justice Department regarding its noncompliance with stormwater discharges.

Suthers said he hopes to iron out an IGA within the next 30 days.

From The Colorado Springs Gazette (Billie Stanton Anleu):

Pueblo County commissioners were gracious but appeared unappeased Monday by Colorado Springs leaders’ promises to resolve stormwater issues that have hit downstream communities hard.

And the Pueblo City Council, in a symbolic gesture, unanimously passed a resolution Monday night to support county efforts to hold Colorado Springs accountable for stormwater problems along Fountain Creek and recommend a 10-year plan in exchange for allowing Colorado Springs Utilities to keep its 1041 permit and commence with the Southern Delivery System…

Work on the first priority project, a detention pond on Sand Creek, starts next week. Colorado Springs has hired Richard Mulledy, a professional engineer who previously worked for the City of Pueblo and most recently has been deputy director of water resources for Matrix Design Group in Colorado Springs, as Stormwater Division manager. He starts work Feb. 22.

While Colorado Springs leaders outlined a long list of measures being undertaken to address the stormwater issue, officials with Colorado Springs Utilities and the city remained baffled by the intertwining of what they see as two separate measures.

Utilities has met every condition of its 1041 project, said SDS Director John Fredell. On April 27, the project is to start pumping 5 million gallons of Arkansas River water a day initially from Pueblo Reservoir to Pueblo West, Colorado Springs, Security and Fountain.

Colorado Springs, meanwhile, is negotiating with the U.S. Environmental Protection Agency, which accused the city in October of neglecting stormwater needs for years. A two-day EPA inspection turned up deteriorating infrastructure, inadequate inspections and excessive sedimentation, among other problems.

At stake is the city’s own water permit.

The effort to hold Utilities’ 1041 permit ransom because of municipal stormwater failures by Colorado Springs is mixing apples and oranges, Suthers and Fredell noted. But Pueblo city and county leaders see the permit for the $825 million SDS as the best bargaining chip to get what they want.

When Suthers assured Pueblo city leaders that more than $250 million worth of stormwater work would be done in 10 years, newly elected Pueblo City Councilwoman Lori Winner cited a CH2M Hill engineering study from 2013 saying the stormwater needs amounted to more than $500 million.

“It’s really a wish list,” Suthers said. “The voters are not going to give me $50 million a year. I don’t want to make any agreement contingent on whether (local anti-tax activist) Doug Bruce likes it or not.”

Because Colorado Springs voters repeatedly voted down stormwater measures in recent years, as Bruce exhorted them to oppose the “rain tax” in 2014, Suthers and the council decided to pay for that need directly from the city budget. The fire and police departments were squeezed and raises frozen in the 2016 budget to find the money.

“I’ll never come up with $500 million,” Suthers said in a rare show of exasperation. “There’s just no way in hell.”

The Pueblo commissioners repeatedly intoned the need for solid enforcement measures in any intergovernmental agreement.

“We as a community have heard a lot of promises from your community for a very long time,” Commissioner Terry A. Hart said. ” . Whatever we do going forward, we can’t base it on mere promises.”

The only “silver lining” in the city’s problems with the EPA is that any resulting federal decree will serve as a mandate, ensuring that the pact with Pueblo County is enforced, Suthers said.

Another enforceable provision would be to designate Utilities, as a long-time city enterprise, to meet the financial requirements through its annual “excess revenue” returns to the city if Colorado Springs failed to meet its stormwater obligation.

Hart questioned whether a fifth branch of Utilities couldn’t be created to handle stormwater. But that would require a change in the City Charter, approval by Colorado Springs voters, who have opposed all recent stormwater measures, and other complex machinations involving ratepayers who don’t live in the city, said Andres Pico, chairman of the Utilities board.

Commissioner Sal Pace questioned whether the SDS couldn’t be turned off if sufficient stormwater work isn’t done, or whether the project could be delayed while a new agreement is drafted.

Neither idea is feasible, however. The SDS is a sprawling system with water treatment plants, pumping stations and precise chemical requirements that cannot be stopped once it gets started. And the notion of delaying it would cause Utilities to lose time on its warranties, some on millions of dollars worth of work and equipment, Suthers said.

Asked what would happen after a 10-year agreement, the mayor said language could be added to renegotiate the pact every 10 years, with a clause for inflationary increases.

“We’re going to continue our negotiations with the county and everybody else involved and try to resolve this issue,” Suthers said Monday evening.

As for the commissioners’ questions earlier in the day, he said, “I thought they brought up good points that can be the basis for more negotiations.”

Leave a Reply