Basin Implementation Plan Update
Ed Tolen, SW Basin 1st Vice Chair, explained that in January a sub-committee was set up to select a local expert to work with the SW Basin Roundtable on updating the Basin Implementation Plan (BIP). From the proposals received the committee chose Harris Water Engineers to be local expert. Steve Harris (Harris Water Engineering) will no longer participate on the Interbasin Compact Committee (IBCC) or the SW Basin Roundtable, and Carrie Padgett, P.E. of Harris Water will also step down from the SW Basin Roundtable. Roundtable elections will take place in October, Officer elections will take place in July.

There will be a team approach to working on the BIP update that will include the SW Basin Roundtable, the Local Experts (Harris Water Engineers), who work with the General Contractor (Brown and Caldwell) and the CWCB.

Matt Lindberg with Brown/Caldwell, the General Contractor, gave a presentation on next steps regarding the BIP review process. The purpose of the review and update is to improve project data, unpack technical update, revisit goals and objectives and invest in process efficiency.

The timeline for the BIP update is as follows:

  • March – August 2020 – Local Expert Workshops, Work Plans and Project lists.
  • September – December 2020 – Basin Analysis/Study
  • January – December 2021 – Update the Basin Implementation Plan
  • December to March 2022 – Incorporate Updated BIP’s into the Water Plan Update
  • To view the full Technical Update to the Colorado Water Plan go here.