Longmont: St. Vrain Greenway restoration 2 – 3 years out

St. Vrain Greenway Trail washout September2013 via Longmont Times-Call
St. Vrain Greenway Trail washout September2013 via Longmont Times-Call

From the Longmont Times-Call (Scott Rochat):

It could take two years before the Greenway can once again be traveled from end to end, according to Kim Shugar, the city’s natural resources manager. And it’ll likely take another year on top of that before it looks like it once did, with its landscaping once again in place.

“It took 20 years to build,” Shugar said. “Even though the river destroyed it in a couple of hours, we are going to get it back open as soon as possible.”

Parts of it won’t have to wait that long; the first re-opened stretches are expected to be done by mid-January. But a lot depends on how much has to be done. The city’s plans show three phases of work:

Phase 1: Repair the trail, areas where the concrete needs to be fixed, but the underlying base is in decent shape. This is the “low-hanging fruit” that has the mid-January date.

Phase 2: Rebuild the trail. These are the harder parts, where the base itself was destroyed in the flood. That work will be bid in December and may be done by March or April.

Phase 3: Redesign the trail. These are the places where the river cut a completely new course, so that either the river or the trail must be moved. This is where the two-year timeframe comes into play, and even that’s a guess, since it depends on what the Army Corps of Engineers decides.

“Until we get direction from the Army Corps of Engineers, we can’t begin design,” Shugar said…

Those wanting to stay posted can check an interactive map on the city’s website, ci.longmont.co.us. A link can be found after clicking on the link for flood information. The map includes “thumbtacks” that can be clicked to show a photo of the area, its current condition and the work that needs to be done.