Mosca wastewater project progressing — the Valley Courier

Wastewater Treatment Process
Wastewater Treatment Process

From the Valley Courier (Phil Ray Jack):

Alamosa County Commissioners (ACC) received an update on the Mosca Wastewater Infrastructure Improvement Project Wednesday.

“The project is moving forward,” Rachel Baird reported , “and we are in the process of applying for the additional funding it will take to complete it.”

In January, the commissioners approved a $1.4 million plan for a new wastewater treatment system in Mosca. For years now, the small community located in northern Alamosa County has wrestled with a failing sewage system and the threats to public health caused by it.

According to some reports , the system has been in disarray for two nearly two decades, threatening residents’ health because the sewage is not being adequately treated before being discharged, and leaching into the area surrounding existing septic tanks. Seven of the 10 septic/leach fields systems have wells located within the minimum 100 foot setback distance, which makes them highly susceptible to contamination.

A preliminary engineering report describing the proposed system had been presented to the county during a previous meeting. Mosca’s new wastewater system will consist of three parts: a collection system, a wastewater treatment facility and a discharge system.

Ken Van Iwarden, who is representing Alamosa County in the process, explained that groundwater tests were conducted on March 17 by the Colorado Water Association. The results will not be known but will provide more information that will help with determining what type of system will be appropriate for the project.

Until the project is completed , the county will continue to regularly pump the failing system because there is no other option, costing county taxpayers upwards of $50,000 annually.

More wastewater coverage here.