Update on the new hydroelectric generation station at the north outlet works at Pueblo Dam

The new north outlet works at Pueblo Dam -- Photo/MWH Global
The new north outlet works at Pueblo Dam — Photo/MWH Global

From The Pueblo Chieftain (Chris Woodka):

It will be awhile before the turbines start spinning, but work continues toward installing hydroelectric generation at Pueblo Dam.

An update on the hydropower project was shared by Kevin Meador of the Southeastern Colorado Water Conservancy District staff at this month’s board meeting.

“We’re working with Black Hills Energy on the pricing of power and what we sell it for. That’s a key piece, and we’re getting close to the nitty-gritty,” Meador told the board.

The district is working with Colorado Springs Utilities and the Pueblo Board of Water Works on a 7-megawatt generation system that would be installed at the North Outlet Works on Pueblo Dam.

The structure was built as part of the Southern Delivery System with design allowing for future hydro connection. It would generate about 20,000 megawatt hours annually and could be completed by 2018.

The total cost of the project is in the $20 million range, and so far about $934,000 has been expended in engineering work.

In January, the Pueblo County planning commission issued a finding of no significant impact and the U.S. Bureau of Reclamation decided an environmental assessment would be needed. Black Hills completed an interconnection study in December and recommended hooking up to the grid at a newly constructed substation which will serve the SDS Juniper Pump Station.

More Southeastern Colorado Water Conservancy District coverage here.