Native Excavating installed 2,265 linear feet of 24-inch sewer pipe and eight manholes this year alone. Excluding lateral connections, about 71% of the main sewer line is complete and the crews are about one week ahead of schedule. Crews will install service connections into the new sewer main while abandoning the existing main, then they’ll test and inspect the new manhole connections and sewer main. Then, the private irrigation systems that were impacted by the construction will be repaired or replaced, such as the systems at City Market Fuel and The Village at Steamboat…
Elsewhere, starting this past week, culverts in four areas of town are being rehabilitated as part of a separate project seeking to upgrade critical water infrastructure.