From The Boulder Weekly (Bob Berwyn):

“After being in a permitting process for more than 10 years, we are pleased to see the release of the Final Environmental Impact Statement for Denver Water’s Moffat Collection System Project,” says Jim Lochhead, Denver Water CEO and manager.

Colorado’s biggest water provider says the project will guard against future shortages on the northern branch of its system and provide more operating flexi bility, make the overall system more resilient to climate change and extreme weather events like floods and fires. And part of the mitigation includes water earmarked for environmental purposes on both sides of the Continental Divide, water that could benefit a sometimes stressed trout population in the South Fork of Boulder Creek.

After scouring thousands of public comments and compiling the voluminous scientific and engineering studies for the Moffat Collection System Project, the federal agency says the new diversion and storage would help avert a potential major Denver Water system failure. The feds singled out Arvada, Westminster and the North Table Mountain Water and Sanitation District as especially vulnerable to raw water shortages without the project.

Release of the final EIS is one of the final steps in the intricate and regulatory ritual required by the National Environmental Policy Act, commonly known as NEPA. Especially for big projects involving public resources, the law is intended as an environmental bulwark. Ten years is a long time, but irrevocable allocation of public resources requires a hard — not a fast — look, the law says…

A few hours after the study was posted, the environmental community targeted media and the public with statements and blog posts from conservation groups, including a stern warning shot from Earthjustice, the legal arm of the green machine. In response to the Corps’ dire warnings of water shortages, some conservation advocates seemed to be saying they’re ready for an all-out battle over the Moffat project.

Hardened battle lines are nothing new in western water wars, but if Winston Churchill were to comment on this one, he might say, “Never have so many battled so hard over so little.”

The Moffat project would reliably deliver 18,000 acre feet of water. That’s enough to comfortably supply a small community for a year, but to keep that number in perspective consider this: All of Denver Water’s reservoirs combined lose more than 25,000 acre feet of water annually to evaporation…

Conflict over the Moffat project may be avoided, since all the parties worked on this collaboratively, says Conservation Colorado advocacy director Becky Long.

“People really rolled up their sleeves and went to work on that plan. … My sense is Denver has been pretty willing to mitigate and negotiate,” says Long, who has deep roots in rural agricultural water use after growing up in the ranch and grazing lands of the Lower Blue Valley, north of Silverthorne.

Even before fully studying the final environmental impact statement, Long says it’s clear that this proposal is different from many past projects because of the huge effort put into mitigating the effects of new diversions and storage, especially on the Western Slope…

“At some point, Denver Water will need a permit from the county,” says Chris Garre, who lives on the south shore and has become leader of a grassroots effort to draw attention to the concerns of area residents.

Standing at one of the stunning overlooks, Garre explained graphically how the landscape would permanently change with construction, including a de-forested rock face at the site of the potential quarry, along with a total inundation of the existing shoreline and the elimination of tens of thousands of trees…

The formal comment period ends in June, but could be extended by another 45 days, with many entities already saying they will request more time. Denver Water execs said they expect a final Corps of Engineers decision on the $360 million project within a year. The decision will be made at the regional Corps of Engineers headquarters in Omaha.

Beyond that, Denver Water still needs several other major permits, including an amendment to a federal hydropower license and a water quality certification under the state-run Clean Water Act standards.

Denver Water spokesman Steve Snyder said the cost of the project, based on a per acre-foot yield, is in line with other water projects along the Front Range.

The first phases of construction including offsite road improvements could start as early as 2017, with dam construction expected to start in 2018 and finish in 2021, with the heaviest construction occurring between 2019 and 2020, Snyder says. All schedules are based upon the permitting schedule and may be delayed or accelerated pending approvals.