From email from Reclamation (Kara Lamb):

It’s Memorial Day weekend and time to kick off my annual communications about run-off.

Some of you might have noticed that we saw some peaking run-off at Willow Creek last week. Inflows to the reservoir were over 900 cfs. As a result, releases from the dam were bumped up to about 450 cfs on May 16th. They did not stay at that level for long.

Going into Memorial Day weekend, inflows from snow melt are anticipated to peak at about 700 cfs. Releases have been adjusted to around 100 cfs as we continue to store behind the dam. We do not plan to increase releases until the reservoir fills or we see much larger peak inflows.

Meanwhile at Granby Reservoir, we continue to release around 70 cfs. The reservoir is at a water level elevation of 8230.5–about 50 vertical feet down from full and the storage content is a little less than half full. The reservoir has started filling with some run-off flows already, bumping up ten feet in elevation over the past couple of weeks. We are anticipating seeing the reservoir water level rise another 20 feet as run-off continues.

From email from Reclamation (Kara Lamb):

It’s Memorial Day weekend! That means it’s time for my annual kick-off e-mail for the run-off and recreation season across the Colorado-Big Thompson Project.

We’re starting to see some run-off come from melting snow right on time for Memorial Day weekend. On the east slope of the C-BT that means we’re seeing snow that melts up in Rocky Mt. Natl. Park during the day run down the rivers, making it to Lake Estes late at night.

To manage the inflows to Estes at night, tonight, May 24 around midnight, we’ll bump up our releases from Olympus Dam to the Big Thompson River to about 250 cfs. The 250 cfs will likely remain in place throughout the holiday weekend.

Lake Estes is at typical water elevation levels for this time of year, fluctuating daily with power generation.

Project water being brought through the Adams Tunnel to Estes moves on to the C-BT’s southern power arm where it is used to generate hydro-electric power at three power plants. Pinewood Reservoir, which sits between two of those plants, is also at typical water elevation levels for this time of year, fluctuating daily with power generation. Likewise, Flatiron Reservoir is also fluctuating daily, as is normal. Those visiting Pinewood and Flatiron for the holiday weekend should be mindful of the daily fluctuations in water levels and please remember that there is NO swimming or boating of any kind in Flatiron.

The pump to Carter Lake has been turned off. Carter is ready for the weekend, sitting about 90% full with a water level elevation of 5748 feet.

Because we are generating hydro-power, the Big Thompson power plant at the mouth of the Big Thompson Canyon by the Dam Store will be running this weekend. Visitors to the area and downstream will notice about 400 cfs being discharged from the plant to the Big Thompson River. To learn more about Reclamation’s hydro-power program, visit here or here.

When the Big T plant goes on, flows to Horsetooth Reservoir will be cut back by about half. Beginning this weekend, around 175 cfs will continue to flow into Horsetooth. Currently, the reservoir is at an elevation of 5414, which is its average starting water level elevation for the recreation season and about 16 feet down from full. The water elevation is still rising.

More Colorado-Big Thompson Project coverage here and here.

Leave a Reply