@Northern_Water overturns #FortCollins’ denial of #NISP pipeline — The Fort Collins Coloradoan

Northern Integrated Supply Project (NISP) map July 27, 2016 via Northern Water.

From The Fort Collins Coloradoan (Jacy Marmaduke):

Northern Water’s board of directors unanimously overturned the city of Fort Collins’ denial of infrastructure associated with the Northern Integrated Supply Project, clearing the way Wednesday for construction of a pipeline and Poudre River diversion in city limits.

Fort Collins’ Planning and Zoning Commission rejected a SPAR (site plan advisory review) application for NISP infrastructure in a 3-2 vote on June 30. But state law allows governing boards to overrule denials of SPAR applications for public infrastructure with at least a two-thirds majority vote.

The Northern Water board’s decision means the water district, after getting the necessary city permits, should be able to build a river diversion on the Poudre at Homestead Natural Area and about 3.4 miles of pipeline in city limits. The diversion and pipeline are part of Northern Water’s plan to release between 18-25 cubic feet per second of the project’s Poudre River diversions through a 12-mile section of the river in Fort Collins before piping it to NISP participants.

NISP would take water from the Poudre and South Platte rivers to deliver an estimated 40,000 acre-feet of water annually to 15 small municipalities and water districts in Northern Colorado, including Fort Collins-Loveland Water District and Windsor. The water would be stored in two new reservoirs: Glade Reservoir, with a capacity of 170,000 acre-feet located northwest of Fort Collins at the mouth of the Poudre Canyon, and Galeton Reservoir, with a capacity of 45,600 acre-feet located northeast of Greeley.