Summer work begins at Glade Reservoir as #NISP awaits federal permit — The #FortCollins Coloradoan #PoudreRiver #SouthPlatteRiver

U.S. Highway 287 runs through the future site of Glade Reservoir. The Larimer county Board of County Commissioners approved the 1041 Land Use Permit for NISP in September, 2020. Photo credit: Northern Water

Click the link to read the article on the Fort Collins Coloradoan website (Sady Swanson and Jacy Marmaduke). Here’s an excerpt:

Crews began conducting rock and soil assessments in June at the site of the planned Glade Reservoir, north of Ted’s Place on U.S. Highway 287. The assessments will give Northern Colorado Water Conservancy District officials site-specific geotechnical and geological information that will inform the design and construction of the Glade Reservoir dam…

The assessment work is expected to continue through November, according to a Northern Water news release. This work includes:

  • Digging a 1,000-foot-long trench at the main dam site to test materials and drill the foundation
  • Building a test pad of embankment material types
  • Producing aggregates and rock fill from quarries and investigating material characteristics
  • This work is being done ahead of the project’s anticipated approval by the U.S. Army Corps of Engineers, which is expected to make its final determination this year. If that happens, construction could start as early as 2023 with completion expected by 2028.

    Northern Integrated Supply Project (NISP) map July 27, 2016 via Northern Water.